Northern Trust approves £693,000 repair plan for Ballymena Health and Care Centre after months of scaffolding


Ballymena Health and Care Centre
Friday 27 November 2026
The Northern Trust has approved a £693,000 plan to repair Ballymena Health and Care Centre, where inspections following storm damage found defects in the roof capping and brickwork high above the ground.
The Ballymena Health and Care Centre first opened to the public over 10 years ago, on 11 January 2016, and was officially opened on 18 February 2016.
The decision comes two months after the Trust expected scaffolding to come down at the Cushendall Road centre. Papers brought to Thursday’s board meeting show the scale of the permanent repair: the protective capping around the centre’s three-storey section is to be replaced, with new steel supports beneath it and sections of brickwork rebuilt.
The Trust says temporary measures have made the affected area safe. Without a lasting repair, it warned, the risk of falling masonry would increase and water would continue to get into the building, potentially putting patients, staff and visitors at risk and disrupting services.
Why the scaffolding went up
The first explanation the Trust gave Love Ballymena came in February, after Storm Chandra damaged the centre in January. Scaffolding gave inspectors access to the roofline for maintenance and a closer look at the building. It was fully in place by 18 February.
By August, local people were asking how much longer it would be there. The Trust said the inspections had identified a problem with the roof capping that needed a permanent fix.
On 20 August, Love Ballymena reported its assessment:
“Remedial works are progressing on site and the scaffolding is expected to be removed by the end of September.”
Five days later, the Health Minister told North Antrim MLA Timothy Gaston that repairs were expected to finish by mid-September. Taking the scaffolding down afterwards was itself expected to take around four weeks.
It was still up on 19 November. Gaston had asked the Minister for a removal date and a breakdown of costs. Applying the Department’s daily hire rate of £230.14, including weekly safety inspections, to the nine months ending on 18 November, he estimated that hire alone could have cost £62,828.22.
The £693,000 repair behind the scaffolding
What began with inspections after January’s storm has grown into a plan to secure the entire roofline of the centre’s three-storey section.
On Thursday 26 November, the Northern Trust board approved the scheme, estimated at £693,000. The Trust has set that sum aside from its 2026/27 backlog maintenance programme, including a 10% allowance for unforeseen costs.
Along the roof edge, new steel supports will hold the replacement capping in place. Contractors will rebuild the affected brickwork and tie it back to the building’s frame. To keep rain out, they will also replace window sills and repair the joints where the roof meets the walls.
When people in Ballymena asked in August how much longer the scaffolding would be there, the Trust expected it to come down by the end of September.
North Antrim MLA Timothy Gaston said the Department of Health had put the daily scaffolding hire charge at £230.14, including weekly safety inspections. Applying that rate from 18 February, when the scaffolding was fully in place, he estimated that hire alone could have cost £62,800 by 18 November.
When the Northern Trust spoke to Love Ballymena in August, it expected the scaffolding to come down by the end of September. The business case approved on Thursday sets out the permanent repairs and their estimated £693,000 cost, but gives no revised date for removing the scaffolding with work completed.