Gaston demands answers over Ballymena Health Centre scaffolding as estimated hire bill tops £62,800 & deadline passes

Writer: Love Ballymena
Love Ballymena
8 hours ago
4 min read
The scaffolding which has been wrapped around Ballymena Health & Care Centre since February 2026.

The scaffolding which has been wrapped around Ballymena Health & Care Centre since February 2026.


Thursday 19 November 2026


Scaffolding remains around Ballymena Health and Care Centre almost seven weeks after the Northern Health and Social Care Trust expected it to be removed, with North Antrim MLA Timothy Gaston estimating that hire charges alone could have exceeded £62,800.


The structure has surrounded the Cushendall Road healthcare facility for much of 2026, following what the Trust said was storm damage and subsequent investigations into problems with the building's roof capping system and high-level masonry.


The Trust told Love Ballymena in August that remedial work was progressing and the scaffolding was expected to be removed by the end of September. However, it remains in place on 19 November, prompting renewed questions about the repair timetable and the cost of keeping it there.



Mr Gaston has now tabled a Priority Written Question to Health Minister Robbie Butler seeking a removal date, details of the work undertaken and a full breakdown of expenditure.


How storm damage led to months of repairs


The scaffolding was first erected following Storm Chandra, which struck Northern Ireland in January, bringing severe weather conditions that prompted inspections at the health centre.


In February, the Northern Trust told Love Ballymena:


“The Northern Trust can confirm that scaffolding has been erected around Ballymena Health and Care Centre to facilitate essential maintenance and building inspections following recent storms.”



Subsequent investigations identified concerns involving the roof capping system and masonry at the upper levels of the building. The Trust later confirmed that the roof capping problems required a permanent solution rather than temporary repairs.


When local people questioned how long the scaffolding would remain, Love Ballymena sought a further update from the Trust in August.


A spokesperson explained:


“The scaffolding at Ballymena Health and Social Care Centre was erected to enable detailed investigations of the roof capping system and high-level masonry following storm damage earlier in the year.


“There have been ongoing concerns with the roof capping system, which now require a permanent resolution.


“Remedial works are progressing on site and the scaffolding is expected to be removed by the end of September.”



That assurance provided the first clear indication of when the structure might disappear from around the prominent healthcare building. Nearly seven weeks beyond that expected deadline, the scaffolding is still standing.


Daily hire charges put estimated cost above £62,800



The financial implications have now become a central concern for Mr Gaston, who says information provided by the Department of Health allows an estimate of the scaffolding hire bill to be calculated.


According to the MLA, the Department confirmed that the scaffolding was fully erected on 18 February 2026 and that the daily hire charge, including weekly safety inspections, is £230.14.


Applying that rate continuously from 18 February to 18 November produces an estimated hire cost of £62,828.22.


That figure is not a confirmed total paid by the Trust. It is a calculation based on the daily rate supplied to the MLA and assumes the same charge applied throughout the period. It also excludes the costs of erecting and dismantling the scaffolding, as well as the investigation and repair work itself.



Mr Gaston said:


“Scaffolding at Ballymena Health and Care Centre could have cost more than £62,800 in hire alone by now, based on the Department’s stated daily rate.”


The continuing hire charge means the estimated bill would rise by approximately £1,611 each additional week if the same daily rate remains applicable.


Repair timetable comes under scrutiny


The Department of Health had previously advised Mr Gaston that remedial works were expected to be completed by mid-September, with scaffolding removed at the earliest opportunity afterwards.


It also indicated that dismantling the structure would take approximately four weeks.



That timetable differs from the earlier expectation given directly to Love Ballymena by the Northern Trust, which anticipated removal by the end of September. Both dates have now passed.


The distinction matters because completion of the roof repairs and removal of the scaffolding are separate stages. Even if the remedial work was finished on schedule, the structure would still need to be dismantled safely.


Mr Gaston is seeking confirmation of whether the repairs were completed by mid-September, whether additional work has been required and what is preventing the scaffolding from being taken down.


He said:


“Yet the scaffolding remains in place now in November. The Minister must explain whether the remedial work was completed on schedule, what work remains outstanding and when the scaffolding will be removed.”



MLA seeks full breakdown of public expenditure


Beyond the daily hire charges, Mr Gaston wants the Department to establish the overall financial cost of the project.


His Priority Written Question seeks the total scaffolding expenditure, including erection, hire and removal, alongside a breakdown of the nature and cost of the repair project to date.


He says the question was due to be answered almost a week ago but that no response had been provided at the time of his statement.


The information requested would establish whether the estimated hire figure reflects actual expenditure and how much additional public money has been spent investigating and addressing the building defects.



Mr Gaston said:


“The Department should provide the figures and explain why the stated timetable has not been met. The public deserve a clear account of how much this work has cost and why the scaffolding is still there.”


Awaiting a confirmed removal date


For people visiting Ballymena Health and Care Centre, the scaffolding has become a longstanding feature of a building that provides healthcare services to the local community.


What began as inspections following January's storm damage developed into a programme of permanent roof repairs, with the expected removal date moving beyond the timetable previously communicated by the Trust.


The immediate issue is now whether those repairs have been completed and when the structure can finally be dismantled.


Mr Gaston's outstanding Assembly question is intended to establish both the revised timetable and the full cost of the work. Until those details are provided, the £62,828.22 figure remains an estimate of scaffolding hire alone, rather than the final bill for the project.


Love Ballymena has asked for a response from Northern Health and Social Care Trust.